Project Sheet
STATE ROAD NETWORK IN CASTILLA - LA MANCHA
Environment · DIRECCIÓN GENERAL DE CARRETERAS. MINISTRY OF TRANSPORT AND SUSTAINABLE MOBILITY
| Field | Value |
|---|---|
| Client | DIRECCIÓN GENERAL DE CARRETERAS. MINISTRY OF TRANSPORT AND SUSTAINABLE MOBILITY |
| Expediente | MA-TO-004 |
| Title | ADVISORY AND COORDINATION ON ENVIRONMENTAL MATTERS RELATED TO CONSTRUCTION WORKS IN THE STATE ROAD NETWORK IN CASTILLA - LA MANCHA |
| Awarded amount (excluding VAT) | €446,593.55 |
| Start date | 15/12/2023 |
| Execution term | 36 months, extendable by 24 additional months |

Main tasks to be carried out
- Verify that the execution procedures take the environmental aspect into account.
- Review and monitor the Environmental Surveillance Plan and its establishment, if not specified in the corresponding Construction Project.
- Preparation of reports on the environmental development of the actions during the works and those established by the EIS (or Environmental Impact Report) once they are completed.
- Technical environmental advisory to the Works Management.
Works covered by the contract
- 23-CR-3490. First Carriageway of the Fuente del Fresno Bypass.
- 13-CR-3790. Puertollano Bypass.
- 12-AB-4540. A-32 Motorway from Linares to Albacete. Section: CM-313 Road Junction - Balazote (West).
- 12-AB-4430. A-32 Motorway from Linares to Albacete. Section: Balazote (West) Junction - Albacete.
- 12-CU-4060. A-40 Motorway. Section: Tarancón-Alcázar del Rey. New junction between the A-40 and the A-3.